"

yy彩票网页版登录地址-yy彩票登录官网首页拥有全球最顶尖的原生APP,每天为您提供千场精彩体育赛事,yy彩票网页版登录地址-yy彩票登录官网首页更有真人、彩票、电子老虎机、真人电子竞技游戏等多种娱乐方式选择,yy彩票网页版登录地址-yy彩票登录官网首页让您尽享娱乐、赛事投注等,且无后顾之忧!

"

 

Jinsha River Xiluodu Hydropower Station
Time:2013-10-11 12:56:45        Word size: Small Middle Large
 

Project overview:concrete hyperbolic arch dam, the maximum height of the dam is 278 meters, total installed capacity is 12.6 million kilowatts, storage capacity is 12.67 billion cubic meters. The project is currently second largest hydropower station in China.

Undertaken project:Cleaning works of dangerous rocks and covering layer at outlets of diversion tunnels and flood discharging tunnel at left bank, construction and support works of diversion tunnel, excavation works at inlet of diversion tunnel, tailrace surge access tunnel work at the left bank, plunge pool, afterby dam work.

 

Copyright ? 2013 by Sinohydro Bureau NO.4 Co.,Ltd. All Rights Reserved

yy彩票网页版登录地址-yy彩票登录官网首页